Our newest project is starting in Prescott, Ontario!

We’re finally getting our boots dirty, and we couldn’t be happier.

On October 15th, 2025, the security fencing went up around the site, with a lot of help from our strong volunteers.

On October 21st, the service crews were making their first cuts into the roadway to connect the water and sewerage lines.

The services were fully hooked up on October 23rd, and an electric pole was also repositioned.

On October 24th, we had some gravel laid down, and the excavators again got to work in scraping the top-soil from the site.

And here on October 27th, 2025, we’re starting to dig down in preparation of laying the foundations.

It’s amazing to see the rapid progress, and we absolutely have to thank all of our supporters, volunteers, and partners.

Stay tuned for more updates!!